PROJECT AT PURATOS CHOCOLATE FACTORY WITH POWER OF 300 KWP – VSIP.II
Total Power  300kWp
Investor CME Solar
EPC Contractor EPC Solar INS
Construction Partner Hung Phat Mechatronics
Installation location Puratos factory, No.51 Street 8, VSIP.II Industrial zone, Thuan An, Binh Duong.
Installation Equipment

Longi Mono – 435Wp Solar panels

Huawei SUN2000-60KTLM0 on-grid Inverter

VIMETCO Aluminum Frame System and Fittings

PROJECT AT PURATOS CHOCOLATE FACTORY WITH POWER OF 300 KWP – VSIP.II

In February 2021, the Puratos rooftop solar power project - CMES with a capacity of 300 kWp at the roof of Puratos chocolate factory, CMES investor and Solar INS general contractor deployed and after 20 days was officially put into operation. operate and put into use. The project is 100% sold to the factory (self-use - using Zero-export solution)

Investment Opportunities

Realizing the load potential of the SCSC cargo terminal (over 1 billion VND per month on electricity bill), along with the ground and roof structure of the station, it is very convenient for the investment in the rooftop solar system, so the investor CMES has come to the decision to invest in a rooftop solar system that combines selling electricity to both the cargo terminal and the EVN grid.

Thanks to the experience in the field of supplying and installing rooftop solar power systems and the successful cooperation in previous projects, Solar INS was selected to be the full-package contractor for this project

 
Challenges

Realizing the load potential of the SCSC cargo terminal (over 1 billion VND per month on electricity bill), along with the ground and roof structure of the station, it is very convenient for the investment in the rooftop solar system, so the investor CMES has come to the decision to invest in a rooftop solar system that combines selling electricity to both the cargo terminal and the EVN grid.

Thanks to the experience in the field of supplying and installing rooftop solar power systems and the successful cooperation in previous projects, Solar INS was selected to be the full-package contractor for this project.

 
Effective solution

Realizing the load potential of the SCSC cargo terminal (over 1 billion VND per month on electricity bill), along with the ground and roof structure of the station, it is very convenient for the investment in the rooftop solar system, so the investor CMES has come to the decision to invest in a rooftop solar system that combines selling electricity to both the cargo terminal and the EVN grid.

Thanks to the experience in the field of supplying and installing rooftop solar power systems and the successful cooperation in previous projects, Solar INS was selected to be the full-package contractor for this project.

 
Project completion

The project, after energizing and officially putting into operation in early April, has met the expectations of the investor and Jin-Yang factory manager, in terms of technical quality, efficiency, and power output. At the same time, it also solves all the challenges posed.

The payback period is only 4.5 - 5 years.
Reduce CO2 emissions by more than 1.4 tons/year
The outstanding performance of the project
Average energy yield 1.6 GWh/year